moving SSAS 2005 database to another drive

Hello,

how can I move the SSAS 2005 database to another drive ? The reason is, I′m running out of space on the current drive.

Thanks a lot for an answer.

Hi,

You can change the Data folder for AS2005, to move all the databases to another location (you cannot have separate locations for databases on the same AS2005 instance). To do that:

1. use the server's properties dialog to specify the new path (from SQL Management Studio, connect to AS2005, right click on the server, Properties, DataDir property) (the change will not become effective immediately, no actual data will be moved)

2. stop AS2005

3. move the Data directory to the drive you want

4. restart AS2005

sql

Friday, March 9, 2012

Moving Reports to another computer Connection String

Hello
I created several Reports using SSRS and SSAS. now i have to move them to another PC, which name is different. is there a way to do this without having to open each report in BIDS and changing the connection string for each Data Source ?
thanks

There are several ways to do this, although it is probably too late for you now to do some of them:

1) use a shared datasource so that you can change only one place

2) use an expression as your connection string, as described here http://msdn2.microsoft.com/en-us/library/ms156450.aspx
... look for the section on "expression-based DataSources" or DataSource Expressions or something like that.

as I said it is too late for those now, you already created the reports, right?

3) write a script that loads each RDL/RDLC as an XML document and fixes the connection string -- or if there are only a handful of reports, just open the XML and do it manually... even manually it is probably faster than loading every report in the designer. But writing such a script to iterate over the contents of a folder and fix the one item you want to fix in each one shouldn't be very hard -- might come in handy later.

4) deploy the reports as-is to the new server and then manually fix their connection strings in the Report Manager interface, again depending on how many this might be pretty quick.

5) deploy the reports as-is to the new server and then use the SQL Studio Management interface to drill down to the Data Sources node for each report and fix it there -- might be faster than the BIDS way since you're not opening the reports

.... ?